The basic renovation of the swimming hall began on February 1.2.2023st of XNUMX. All facilities in the swimming hall are closed due to renovation.
Situation on 20.9.2024 September XNUMX:
Filling work is underway in the yard, after which we will start making the surfaces. On the park side, the installation work of a large glass wall is underway. In the installation work, diesel hoists are used to guarantee the safety of the work and they may cause intermittent noise. On the park side, construction of the retaining wall and ramp for the swimming hall will also start soon
for chemical storage. Sheeting and finishing works are underway on the water roof.
Building engineering and tiling work continues inside. The main focus of tiling has shifted to the pool area. Furniture installation has also started inside.
The pictures have captions describing the work phase shown in the picture. You can display the caption by clicking on the image.